Normally hydro plant doing major overhaul around 10 years for a cycle. Why we need such work to be carry out?

The main reason for setting up overhaul is to prevent unscheduled outages from failure of equipment. Since a machine which already run for a long period have lot of wear and tear and need to be treated well to make it last longer.

In order for the overhaul to proceed smoothly and to accomplish all the work required, planning should start well before the overhaul starts.

I am going to prepare roughly on what we have to do or prepare before we can carry out such a big job. Maybe it will takes some time to complete all the checklist. Anyway I will try to find out the data first before write an entry about hydro major overhaul.

Email ThisBlogThis!Share to XShare to Facebook
Posted in General | No comments
Newer Post Older Post Home

0 comments:

Post a Comment

Subscribe to: Post Comments (Atom)

Popular Posts

  • CCI Sulzer Valve and Drag Control Valve
    Description: PV6 CCI Part Number: 103.215.282.001 Valve Serial Number: Valve Control Description: Seal Set PV6 CCI Part Number: 000.101.000....
  • List of Hydro Power Plant in Malaysia
    Hydropower Peninsular Malaysia Tenaga Nasional Berhad operates three hydroelectric schemes in the peninsular with an installed generating ca...
  • Foxboro Malaysia
    Yesterday, I posted about the Foxboro Absolute Pressure Transmitter . Then searching around the internet for their support and services in M...
  • Sheet Metal
    Sheet metal is simply metal formed into thin and flat pieces. It is one of the fundamental forms used in metalworking, and can be cut and be...
  • SJ Gelugor Power Station
    Stesen Janakuasa Gelugor is owned by TNB. 
  • Hydroelectric in Malaysia
    Terengganu Hydroelectric Dam 400MW installed capacity Sultan Mahmud Power Station 4X100MW Cameron Highlands Dam 262MW installed capacity Jo...
  • Lumut or Segari Power Plant Photo
    Lumut or Segari Power Plant Perak View at Night Aerial view of Segari Power Plant and GB3 Combined Cycle Power Plant My last articles about ...
  • Langkawi Power Plant Teluk Ewa, Langkawi Kedah
    Langkawi Power Plant Teluk Ewa, Langkawi Kedah Langkawi Power Plant Teluk Ewa, Langkawi Kedah
  • Hydroelectricity Explained
    Hydroelectricity Itaipu Brazil/Paraguay Dam scene at night Close up view of dam: Itaipu Brazil/Paraguay Hydroelectricity dam Hydroelectric...
  • Sultan Iskandar Power Station
    Sultan Iskandar Power Station or Pasir Gudang  Power Station is located at Pasir Gudang  Johor.  Type of Plant Thermal (2 ST), combined cycl...

Categories

  • Analyser
  • Bently Nevada
  • Boiler
  • Car
  • Card
  • Coal and Ash
  • DCS
  • Electrical
  • Electro Chlorination Plant
  • Equipment
  • Events
  • Gauge
  • General
  • Generator
  • Heat Exchanger
  • Hydraulic
  • Hydroelectricity
  • Hydrolectricity
  • IT
  • Microrec
  • Mill
  • Miscellaneous
  • Motor
  • Package Equipment
  • PLC
  • Power Plant
  • Pump
  • Pump House
  • Samsung
  • Solar Energy
  • Summary Report
  • Switch
  • System
  • Terminal Block
  • Test Equipment
  • Testing and Commissioning
  • Tools
  • Toyota
  • Transducer
  • Transmitter
  • Turbine
  • Valve and Fitting
  • Water Treatment Plant

Blog Archive

  • ►  2014 (1)
    • ►  January (1)
  • ►  2013 (41)
    • ►  December (9)
    • ►  November (20)
    • ►  September (2)
    • ►  July (1)
    • ►  June (2)
    • ►  May (2)
    • ►  April (1)
    • ►  February (2)
    • ►  January (2)
  • ►  2012 (39)
    • ►  December (2)
    • ►  November (1)
    • ►  October (9)
    • ►  September (1)
    • ►  July (1)
    • ►  June (3)
    • ►  April (5)
    • ►  March (9)
    • ►  February (5)
    • ►  January (3)
  • ►  2011 (82)
    • ►  December (2)
    • ►  November (2)
    • ►  October (4)
    • ►  September (1)
    • ►  August (7)
    • ►  July (11)
    • ►  June (12)
    • ►  May (6)
    • ►  April (13)
    • ►  March (14)
    • ►  February (7)
    • ►  January (3)
  • ▼  2010 (66)
    • ▼  December (16)
      • Way to Jimah Coal Fired - Map
      • Test your brains... How many legs do you see?
      • 3 Virtual Turbines: Pelton, Francis and Kaplan
      • Jimah Power Plant Chimney
      • Chocolate eaters may have healthier hearts
      • Mill Coal Grinder
      • Vibrosystm For Hydroelectric Applications
      • Hydro Plant Major Overhaul
      • DCS Vs SCADA
      • Pergau Hydroelectric 600MW
      • Purchased Nokia C6-01 at Giant Mall
      • How much this Philip AVENT Baby Temperature Monito...
      • Manjung Power Station - 2100MW Coal Fired Power P...
      • Simcard error
      • What is the Main Inlet Valve?
      • New Vibration System - Vibrosystm
    • ►  November (17)
    • ►  October (8)
    • ►  September (19)
    • ►  August (2)
    • ►  July (1)
    • ►  May (1)
    • ►  February (2)
  • ►  2009 (33)
    • ►  November (6)
    • ►  October (7)
    • ►  September (6)
    • ►  August (1)
    • ►  June (3)
    • ►  May (1)
    • ►  March (2)
    • ►  February (4)
    • ►  January (3)
  • ►  2008 (182)
    • ►  December (1)
    • ►  November (2)
    • ►  October (7)
    • ►  September (11)
    • ►  August (26)
    • ►  July (6)
    • ►  June (7)
    • ►  May (9)
    • ►  April (21)
    • ►  March (43)
    • ►  February (22)
    • ►  January (27)
  • ►  2007 (2)
    • ►  December (1)
    • ►  November (1)
Powered by Blogger.

About Me

Unknown
View my complete profile